Showing posts with label wind. Show all posts
Showing posts with label wind. Show all posts

Tuesday, February 24, 2009

Another wind turbine planned for Slough

lock your doors, an application is in for another baby-eating wind-turbine in Slough!

Well, almost - there's an application on the Slough Council planning website

INSTALLATION OF A 40M GUYED WIND MONITORING MAST WHICH WILL BE REQUIRED TO MONITOR SITE CONDITIONS FOR A PERIOD OF 3-12 MONTHS 
The average wind-speed at this site, just north of Wexham Hospital, is about 6.4 m/s, which on a 3MW turbine means about 5GWh p/year. I don't know who is putting this application in, but at least they seem to be more serious and prepared than the last lot in Cippenham
Speaking with some of the councillors on the planning committee since the fiasco of the last hearing, there still isn't a policy on renewable energy in Slough, but they suggested that I raise this with the Scrutiny committee

maybe

Monday, August 25, 2008

Cippenham Wind-farm

There's a proposal for a new wind-farm just down the road, in Cippenham, about here.

A letter in the local paper last week (Slough Observer 22/8/08), pretty much the first comment there's been on the proposal, used figures from the local opposition group WindRats to say both that the developer would be making nearly £3m a year from the proposal (assuming full capacity) and that the wind speed is so low in the local area that it wasn't worth bothering with. Which is it?!

As usual, the truth lies somewhere these points (though in normal debate, different sides, not the same, tend to make the contradictory statements). Here's my letter and the workings behind it:



Tom Williams (Letters last week) states that his opposition to the proposed Cippenham wind turbine is based upon available sourced data, so perhaps his opposition could be turned into support. He rightly states that the average annual wind speed for the proposed site is just under 6m/s, a speed which would, from the manufacturers own statistics, produce about 0.25MW. This is only about one twelfth of it's maximum power (though Mr Williams and the Windrats.com website seem to assume 100% production when coming up with their £2.7 million figure), but this is only part of the story.

As any driver knows, wind-resistance increases significantly more the faster you get, requiring more petrol to accelerate from say 70-80 mph than from 20-30mph. This explains the difference in design between the Volvo and the Porsche. Happily, this effect also works in reverse - the faster the wind blows, then proportionally more energy a turbine can extract from the wind. In practice, what this means is that you cannot get an accurate estimate of the potential output of a turbine from the base average wind speed alone, but would need to survey the actual speeds on site over a period of months. I have no idea if this research has been done, but by using an estimation method used by the wind-energy industry, I calculate that this site and turbine would produce over 5000MW hours of electricity per year, enough for about 1200 houses and saving nearly 3000 tonnes of carbon dioxide emissions in the process (the exact workings available at 2cheap2meter.blogspot.com ).

As these figures approximately match the developer's figures, I hope that Mr Williams will now join me in giving support to this proposal on economic grounds. Wind-power is going to become more common as we struggle to meet our rising energy demands from dwindling and polluting resources such as gas and coal, and to me are far preferable to the "energy-from-waste" incinerators currently operating on the Trading Estate and soon in Colnbrook.




OK, the maths.

This is based on the formula given in the Beurskins and Jensen article "Economics of wind-energy, Prospects and Directions" in the July/Aug 2001 edition of "Renewable Energy World". It looks to give an estimate of the energy available from a particular wind-turbine site. It's only an estimate, and you need to do a proper site survey and then match that to the exact specifications of the turbine you intend to fit. But it gives you an idea.

The turbine is sited at grid reference SU946797 (SU9479), which from the UK Wind Energy Database gives an average wind speed at 45m above ground level (agl). However, the actual turbine will be higher than that, so the developers suggest a speed of 6.4 m/s

The basic formula is :

Annual energy production (kWh) = K Vm3 At T

Nice. What this actually means is:
K = 3.2 = a factor based upon the relationship between standard turbine efficiency and wind-speed distribution.
V - is the cube of the average wind-speed for the site. This is the key, wind-energy is all based on the fact that the energy you get is all based on the cube of the wind-speed. This means you don't get much to start with, but it starts to rise rapidly as the wind-speed increases. For our basic speed of 5.8 m/s this is 195, 262 for the higher estimate.
A - the swept area of the blade. It's expected to be 90m diameter, so that's 45 m radius, which is (PIr2) 6352m2
T is the number of turbines, which in this case is one.


So, multiplying those together, we have either:
3.2 * 195 * 6352 * 1 = 3,972, 512 kWh (3,972 MWh / 3.972 GWh) per year, or
3.2 * 262 * 6352 * 1 = 5,337, 294 kWh (5,337 MWh / 5.337 GWh) per year

To put this in some sort of context, the average household uses 4478kWh p/year of electricity, so dividing the total amount of energy expected to be produced by this household average tells us how many houses could be powered by the turbine, between 887 and 1192.

Measuring CO2 emissions and what might be saved is a bit of dark art, depending mainly on which energy source you say you're replacing (measuring against coal makes you look good, hydro less so, the most recent energy mix is the fairest, but it's still a guess), but the latest figure I've a respectable source for is 0.527kg for each kilowatt hour of energy generated.

So, to calculate the theoretical amount of CO2 saved, multiply the expected energy generation from the turbine by this figure of 0.527kg, giving a figure of between 2,093,513.58kg (2094 tonnes) and 2,812,753.82kg (2,812 tonnes).

This is pretty much in line with what the developer estimates (section 3.12, page 9) for a Vestax 3MW turbine.

And it's both a lot smaller and cleaner than the Slough Estates CHP/incinerator and the now-legendary Colnbrook incinerator ...

Tuesday, May 6, 2008

When wind turbines go bad

A whole blog dedicated to malfunctioning wind turbines ...

http://whenwindturbinesgobad.blogspot.com

but out of context --- it'll be interesting to compare the actual audited dangers from wind-turbines, as opposed to coal (hugely lethal on a hardly noticed scale) or nuclear (usually extremely safe, apart from the odd continent-poisoning catastrophe). From what I've seen, the biggest danger associated with wind-turbines is the sudden "thump" when you fall off

Thursday, May 1, 2008

Darrington Wind Farm

The village in Yorkshire I grew up in, Darrington, is being split over a proposed new wind-farm development. Well, "split" is probably the wrong word, "uninamously enraged" is probably more appropriate, at least to the people I've spoken to.

It doesn't seem that the Bankable Models Which Enable Local Community Wind Farm Ownership guidelines are being followed particularly closely, and that a landowner has done a deal with a developer, with the locals feeling as if they're having a huge development dumped on their doorstep, to provide benefit for others, with little to them.

A local campaign group has been set up - the Pontefract Windfarm Action Group, who have been active in raising awareness of the potential impact the turbines could have. One of the earlier actions was to raise a blimp to the approximate height and location of the highest point of the turbine tip:


I'll keep tracking the progress of both the wind farm and the local campaign, but it was worth looking at a map of the local area:



by the side of the wind-farm, between the nearest houses, is the A1 dual carriageway, and just to the north is Ferrybridge, the coal-fired power station that marks the beginning of "Megawatt Valley", target of the first Climate Camp.

So the proposed turbines are undoubtedly quite big, but will they have the impact on the local environment as claimed by the local action group?